Block C - Gable Town-house

Block C - Gable Town-house
- Property Type
- Townhouse
- Size
- 3 bedrooms
- Delivery - July 2025
- E3: Two townhouses on Ravensbury Grove
- Delivery - December 2025
- Three townhouses on Morden Road
Completed100%
Follow the progress of Block C - Gable Town-house from the first brick!
The External Works
Start June 2025Expected to end 2 Townhouses - July 2025, 3 Townhouses - December 2025
Status: completed
All that remains now is to open up the site and tidy the grounds. There's a little housekeeping to complete before we can welcome residents/home owners to their new homes.
This milestone includes
Hard Landscaping
Start June 2025Expected to end 2 Townhouses - July 2025, 3 Townhouses - November 2025
At this stage, the team will lay the final groundwork. This includes installing public lighting pedestals, paving the driveways and installing fencing and garden fixtures. During this stage, the site will be cleared of all waste, leftover materials, and unnecessary equipment.
Landscaping
Start June 2025Expected to end 2 Townhouses - July 2025, 3 Townhouses - November 2025
Once the site is clear the landscapers and gardeners will install all the external furniture, fixtures and plant the trees, shrubs and lawns.
Technical Tour
Start July 2025Expected to end 2 Townhouses - July 2025, 3 Townhouses - November 2025
The site will be inspected in preparation for the final hand over.
The green light
Start July 2025Expected to end 2 Townhouses - July 2025, 3 Townhouses - January 2026
It is only after we are 100% satisfied that all work has been successfully carried out that we finally sign-off on the homes and hand it over to the new residents. It’s time for you and your family to enjoy your new home.